Q.1 Which of the following elements is not normally common in projects?
a. Uniqueness
b. Uncertainty
c. No defined end point
d. An objective
_________________________________________________________
Q.2 Which is the first stage in the project management model?
a. Project planning
b. Project definition
c. Understanding the project environment
d. Project control
____________________________________________________________
Q.3 A Gantt chart is used to show a project timeline diagrammatically.
a. True
b. False
______________________________________________________________